Question
Mr Richard Holden
Conservative — Basildon and Billericay
To ask the Secretary of State for Transport, what assessment she has made of the potential impact of i) timetable planning, ii) signalling and iii) freight pathing margins on barrier down-times at level crossings; and how Network Rail monitors and reports
Answer
Keir MatherNetwork Rail is responsible for assessing the impact of timetable changes, freight paths and upgrades to signalling on level crossing down-time, as part of its overall management of level crossings on the rail network. These arrangements are kept under re...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 93225) →