Written Question·Department for Transport·UIN 96694
Level Crossings
Tabled: 3 December 2025
Answered: 17 December 2025
Question
Mr Richard Holden
Conservative — Basildon and Billericay
To ask the Secretary of State for Transport, pursuant to the Answer of 28 November 2025 to Question 93226 on Level Crossings, for what reason responsibility for assessing and managing level-crossing down-time rests solely with Network Rail rather than bei
Answer
Simon LightwoodLevel crossings form part of the rail estate and legal responsibility for their safe operation falls to the relevant infrastructure manager, such as Network Rail. Infrastructure managers must operate level crossings in line with their statutory duties but...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 96694) →