Question

James McMurdock

Independent — South Basildon and East Thurrock

To ask the Secretary of State for Transport, whether Network Rail has provided her with data on (a) barrier-down times, (b) duration of delays or (c) frequency of freight movements at the East Tilbury Level Crossing.

Answer

Keir Mather
At this level crossing, there are around 150 scheduled passenger trains passing through each day and up to 45 freight services in both directions per day. During the last risk assessment, Network Rail identified that there were 102 level crossing activati...
ⓘ