Written Question·Department for Transport·UIN 110096
Lower Thames Crossing: Cost Benefit Analysis
Tabled: 2 February 2026
Answered: 10 February 2026
Question
Mr Richard Holden
Conservative — Basildon and Billericay
To ask the Secretary of State for Transport, whether her Department has included the foregone Dartford Crossing toll revenues in the Lower Thames Crossing project’s cost–benefit analysis.
Answer
Simon LightwoodIn line with departmental guidance, cost-benefit analysis for the Lower Thames Crossing is ongoing and incorporates potential impacts at the Dartford Crossing. These include the loss of toll revenue and the transfer of operations, maintenance and renewal ...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 110096) →