Written Question·Department for Transport·UIN 110703
Lower Thames Crossing: Excavation
Tabled: 3 February 2026
Answered: 11 February 2026
Question
James McMurdock
Independent — South Basildon and East Thurrock
To ask the Secretary of State for Transport, what proportion of soil excavated as part of the Lower Thames Crossing construction will be a) re-used on site, b) recycled or c) disposed of off-site.
Answer
Simon LightwoodThe Lower Thames Crossing project aims to reuse between 90% and 95% of the soil it excavates on site. This material will be used to create new public parks, embankments and earth bunds, helping to screen the route from the local community. The remaining m...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 110703) →