Written Question·Department for Transport·UIN 37087
M25: Repairs and Maintenance
Tabled: 10 March 2025
Answered: 14 March 2025
Named DayQuestion
Zöe Franklin
Liberal Democrat — Guildford
To ask the Secretary of State for Transport, for what reason hon. Members representing local constituencies were recently informed of delays to the completion of M25 junction 10 works; and what the cost to the public purse is of those delays.
Answer
Lilian GreenwoodThe project has been delayed due to a number of factors. Severe weather, with unexpected heavy rainfall since October 2023 caused poor ground conditions. This postponed planned winter work and required a redesign of embankments and drainage. Additionally,...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 37087) →