To ask the Secretary of State for Transport, when any assessment by National Highways of temporary slip roads at Junction 38 of the M6 was undertaken; and whether the findings of that assessment informed the current construction programme.
Answer
Simon LightwoodNational Highways first assessed the potential for temporary slip roads during the project’s optioneering stage in 2019. Further consideration took place during early design development, and the option was not taken forward at that time due to spatial con...
ⓘ