Written Question·Department for Transport·UIN 104693

M6: Repairs and Maintenance

Tabled: 12 January 2026
Answered: 19 January 2026
Named Day

Question

Tim Farron

Liberal DemocratWestmorland and Lonsdale

To ask the Secretary of State for Transport, whether he will instruct National Highways to meet with BWB Consulting and Kier in an engineer-to-engineer review of proposals for temporary slip roads at Junction 38 of the M6.

Answer

Simon Lightwood
National Highways has facilitated discussions between BWB Consulting and Kier engineers, including a meeting held on 17 December 2025 to review proposals for temporary slip roads at Junction 38. A further update on temporary slip roads will be provided at...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 104693) →