Written Question·Department for Transport·UIN 19013

Motorways: Leeds

Tabled: 10 December 2024
Answered: 16 December 2024

Question

Jerome Mayhew

ConservativeBroadland and Fakenham

To ask the Secretary of State for Transport, what estimate her Department has made of the completion date of the M621 Junction 1-7 enhancements.

Answer

Lilian Greenwood
The schemes in question are in different stages as follows: Four schemes have been completed and are open to traffic.Scheme NameCompletion DateM621 Junction 1-7 EnhancementsCompleted September 2024A585 Windy Harbour to SkippoolCompleted March 2024A19 Down...