Written Question·Department for Energy Security and Net Zero·UIN 101959
National Energy System Operator: Members
Tabled: 2 January 2026
Answered: 12 January 2026
Question
Blake Stephenson
Conservative — Mid Bedfordshire
To ask the Secretary of State for Energy Security and Net Zero, if he will impose a duty on the National Energy System Operator to inform hon. Members of connection applications in their constituencies.
Answer
Michael ShanksNetwork connection applications are confidential to the parties involved before the point of a contract being signed, but details of generation and storage transmission connection agreements are published in the Transmission Entry Capacity Register TEC Re...
ⓘ