Question

Alex Mayer

LabourDunstable and Leighton Buzzard

To ask the Secretary of State for Energy Security and Net Zero, if his Department will make an assessment of the potential merits of reprioritising the grid connection queue to favour viable projects with planning consent over (a) stalled and (b) speculat

Answer

Michael Shanks
Government is working at pace with Ofgem, the Electricity System Operator (ESO), and network companies to accelerate electricity network connections. The ESO is developing proposals with stakeholders to raise requirements to obtain and retain a connection...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 3423) →