Written Question·Department for Energy Security and Net Zero·UIN 23388
National Grid: Construction
Tabled: 13 January 2025
Answered: 16 January 2025
Named DayQuestion
James Cartlidge
Conservative — South Suffolk
To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 5 December 2024 to Question 17189 on National Grid: Costs of the Western and Eastern Links, if he will make an estimate of the time for delivering the onshore option
Answer
Michael ShanksAt the time of Ofgem’s decision for Eastern Green Link (EGL) 1&2 Final Need Case, an onshore option was expected to be delivered by 2036, based on information provided by the Transmission Owner, National Grid Electricity Transmission. It was not inclu...
ⓘ