Written Question·Department for Energy Security and Net Zero·UIN 35333

National Grid: East of England

Tabled: 4 March 2025
Answered: 7 March 2025
Named Day

Question

James Cartlidge

Conservative — South Suffolk

To ask the Secretary of State for Energy Security and Net Zero, if (a) his Department and (b) Ofgem will make an estimate of the cost of the (i) sealing end compounds and (ii) other costs associated with the construction of the (A) underground and (B) oth

Answer

Michael Shanks
It is the responsibility of the developers of electricity network projects – in this case National Grid Electricity Transmission (NGET) - to propose the route and obtain planning permission for that route. NGET presented cost estimates for the Norwich to ...
ⓘ