Written Question·Department for Energy Security and Net Zero·UIN 35333
National Grid: East of England
Tabled: 4 March 2025
Answered: 7 March 2025
Named DayQuestion
James Cartlidge
Conservative — South Suffolk
To ask the Secretary of State for Energy Security and Net Zero, if (a) his Department and (b) Ofgem will make an estimate of the cost of the (i) sealing end compounds and (ii) other costs associated with the construction of the (A) underground and (B) oth
Answer
Michael ShanksIt is the responsibility of the developers of electricity network projects – in this case National Grid Electricity Transmission (NGET) - to propose the route and obtain planning permission for that route. NGET presented cost estimates for the Norwich to ...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 35333) →