Written Question·Department for Energy Security and Net Zero·UIN 49127
National Grid: Tempsford
Tabled: 29 April 2025
Answered: 8 May 2025
Question
Ben Obese-Jecty
Conservative — Huntingdon
To ask the Secretary of State for Energy Security and Net Zero, what assessment has been made of the adequacy of the grid connections between the proposed new town at Tempsford and the Eaton Socon sub-station to facilitate a new town.
Answer
Michael ShanksOfgem regulates the network companies to ensure they are investing to operate, maintain and upgrade electricity infrastructure. For the next transmission and distribution network price controls, Ofgem has identified the need for significant investment in ...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 49127) →