Written Question·Department for Energy Security and Net Zero·UIN 24535
National Grid: Wales
Tabled: 16 January 2025
Answered: 21 January 2025
Named DayQuestion
Llinos Medi
Plaid Cymru — Ynys Môn
To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the potential impact of Ofgem's decision to allow a pause in new grid connections on the ability of the (a) Alaw Môn and (b) Maen Hir energy projects to connect
Answer
Michael ShanksGrid connections for individual projects are a matter for the National Energy System Operator (NESO) and the network companies. The short pause on connection applications for generation customers is a necessary transitional step in delivering fundamental ...
ⓘ