Jerome Mayhew

ConservativeBroadland and Fakenham

To ask the Secretary of State for Transport, pursuant to the Answer of 29 January 2026 to Question 108013, whether the Department has identified any financial year in which the cumulative efficiency savings attributed to Network Rail are expected to excee

Answer

Simon Lightwood
Network Rail's overall Control Period 7 (running from April 2024 to March 2029) efficiency target is £3.9 billion, which it remains on track to achieve. This will significantly exceed the cumulative cost in Control Period 7 of the major technology investm...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 111814) →