Written Question·House of Commons Commission·UIN 20032
New Palace Yard: Repairs and Maintenance
Tabled: 13 December 2024
Answered: 7 January 2025
Question
Greg Smith
Conservative — Mid Buckinghamshire
To ask the hon. Member for Blaenau Gwent and Rhymney, representing the House of Commons Commission, whether the work for vehicle entry and exit in New Palace Yard is on (a) time and (b) budget.
Answer
Nick SmithThe most recently approved Business Case for the works in New Palace Yard anticipated a completion date of between October 2024 and March 2026. This range takes into account identified risks that may occur over the life span of the project, for example ma...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 20032) →