Question

Olly Glover

Liberal DemocratDidcot and Wantage

To ask the Secretary of State for Transport, what recent progress has been made on the Northumberland Line; and what estimate she has made of the date by which that work will be completed.

Answer

Lilian Greenwood
Recent progress on the Northumberland Line includes completion of track and signalling upgrades which have allowed driver training to commence, and the stations at Ashington, Newsham and Seaton Delaval nearing construction completion ahead of undergoing a...