Written Question·Ministry of Defence·UIN 21447

Nuclear Submarines: Decommissioning

Tabled: 19 December 2024
Answered: 13 January 2025

Question

Graeme Downie

LabourDunfermline and Dollar

To ask the Secretary of State for Defence, how much funding he has allocated to the submarine dismantling programme for each of the next five years.

Answer

Maria Eagle
The Department does not release spending profiles for individual programmes. However, I can confirm the latest Whole Life Cost for the Submarine Dismantling Project, as published in the Department’s 2023 Government Major Projects Portfolio data, is £298 m...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 21447) →