Written Question·Department for Energy Security and Net Zero·UIN HL15461

Office for Nuclear Regulation: Design

Tabled: 12 March 2026
Answered: 26 March 2026

Question

To ask His Majesty's Government what generic design assessments the Office for Nuclear Regulation are currently undertaking; and when they expect each of those assessments to be completed.

Answer

The ONR are currently undertaking two GDAs, step three of the Rolls Royce SMR and step two of the Holtec SMR-300. Publication of the completion dates for those processes is a matter for the regulators, including the ONR, and the Requesting Parties. These ...
ⓘ

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN HL15461) →