Written Question·Restoration and Renewal Client Board·UIN 115411
Palace of Westminster: Repairs and Maintenance
Tabled: 24 February 2026
Answered: 3 March 2026
Named DayQuestion
Wendy Morton
Conservative — Aldridge-Brownhills
To ask the hon. Member for Blaenau Gwent and Rhymney, representing the Restoration and Renewal Client Board, with reference to the stated annual cost of delay of £70 million and the estimated additional £250–350 million annual inflationary impact, what me
Answer
Nick SmithIt is estimated that the cost of delaying starting the delivery phase of the Restoration and Renewal (R&R) Programme is around £70m per year at current prices. It is estimated that there would be a further £250m to £350m in the inflationary impact on ...
ⓘ