To ask the Secretary of State for Health and Social Care, what progress has been made on the the construction of the new A&E unit at Pilgrim Hospital in Boston; and when he expects the construction to be completed.

Answer

Karin Smyth
The new build and refurbishment of the Emergency Department and Urgent Treatment Centre at the Pilgrim Hospital is taking place in two phases. The first phase, which is a new build, is on track to be completed by February 2025, with the subsequent refurbi...