Written Question·Treasury·UIN 113719

Private Finance Initiative

Tabled: 20 February 2026
Answered: 2 March 2026

Question

Alex Burghart

ConservativeBrentwood and Ongar

To ask the Chancellor of the Exchequer, what data (a) her department and (b) NISTA holds on the number of PFI contracts which are due to expire in each of the next three years; and what guidance has been given to central government on PFI expiry and next

Answer

James Murray
HM Treasury publishes aggregate information on PFI and PF2 projects annually, including data on contract expiry dates. NISTA has published guidance for contracting authorities on managing PFI contract expiry and next steps.