Written Question·Department for Transport·UIN 10227
Railway Stations: Access
Tabled: 21 October 2024
Answered: 24 October 2024
Named DayQuestion
Laurence Turner
Labour — Birmingham Northfield
To ask the Secretary of State for Transport, how many planned station upgrades under Network Rail's Access for All scheme were (a) cancelled and (b) deferred during Control Period 6 in each region.
Answer
Simon LightwoodUnder the previous government, changes were made to the Control Period 6 Access for All (AfA) programme at the following stations:Queens Park (London) and Battersea Park (London) - AfA funding was withdrawnPeckham Rye (London) - scope was incorporated int...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 10227) →