Written Question·Department for Transport·UIN 42988

Railway Stations: Access

Tabled: 31 March 2025
Answered: 3 April 2025
Named Day

Question

Mr Paul Kohler

Liberal DemocratWimbledon

To ask the Secretary of State for Transport, how many railway stations underwent development where (a) full step-free access and (b) only passive provision was provided between 2019 and 2024.

Answer

Simon Lightwood
During the period 2019 – 2024, 66 major accessibility interventions were delivered at 63 different stations under the Access for All Programme, 4 of which were fixed funding contributions through the Access for All mid-tier programme.