James Cartlidge

Conservative — South Suffolk

To ask the Secretary of State for Transport, if she will take steps to expedite the approval process for (a) the Ely Area Capacity Enhancement and (b) upgrades to the Haughley Rail Junction.

Answer

Lilian Greenwood
Despite its public statements of support, the previous government made no funding available for the Ely Area Capacity Enhancement (EACE) or upgrades to Haughley Junction. The Chancellor has been clear about the state of the nation's finances and has launc...
ⓘ