Written Question·Department for Energy Security and Net Zero·UIN 99997
Renewable Energy: Landfill
Tabled: 15 December 2025
Answered: 23 December 2025
Question
Jayne Kirkham
Labour (Co-op) — Truro and Falmouth
To ask the Secretary of State for Energy Security and Net Zero, with reference to his Department's policy paper on the UK methane action plan, published on 29 October 2025, what his planned timeline is for implementing a transitional support mechanism for
Answer
Katie WhiteGovernment is aware that support under the Renewables Obligation (RO) scheme will end for existing landfill gas generators from April 2027, which could affect the commercial viability of these generators. We recognise the importance of providing commercia...
ⓘ