Written Question·Ministry of Defence·UIN 52584

Rifles: Costs

Tabled: 15 May 2025
Answered: 27 May 2025
Named Day

Question

Mr Mark Francois

ConservativeRayleigh and Wickford

To ask the Secretary of State for Defence, what is the total cost of the Royal Marines’ Knights Armament Stoner 1 (KS-1) rifle programme, including (a) optical and thermal sights and suppressors and (b) all associated equipment; and how much of this budge

Answer

Maria Eagle
The Knight Stoner KS-1 has been procured by Royal Navy as part of the Future Commando Force Transformation. The total cost of this rifle to the Programme is £30.422 million, of which, £22.887 million has been spent to date.