Adam Dance

Liberal DemocratYeovil

To ask the Secretary of State for Transport, what plans she has to ensure that at least 50 per cent of the revenue from the lane rental scheme is reinvested in (a) road resurfacing and (b) pothole repairs.

Answer

Lilian Greenwood

Charges for works that overrun are already set at up to £10,000 per day. The Government announced in December that we will apply overrun charges to weekends and bank holidays. We also announced that local authorities operating lane rental schemes will be required to spend 50% of surplus lane rental charges on highway maintenance, The regulations implementing these changes will be laid later in 2025. They will also double the level of fixed penalty notices available for some street works offences.