Mr Richard Holden

Conservative — Basildon and Billericay

To ask the Secretary of State for Transport, what estimate her Department has made of the potential (a) cost of and (b) return per pound spent on each scheme in the (i) Strategic Road Network and (ii) Major Road Network and Large Local Major Programmes (A

Answer

Lilian Greenwood
The total estimated cost of committed schemes in the Roads Investment Strategy (RIS) at planning stage (excluding Lower Thames Crossing) is £8.5 billion, and for schemes under construction the total is £4.1 billion. The total estimated cost of the schemes...
ⓘ