Written Question·Department for Transport·UIN 2143
Roads: Construction
Tabled: 29 July 2024
Answered: 3 September 2024
Named DayQuestion
Mr Richard Holden
Conservative — Basildon and Billericay
To ask the Secretary of State for Transport, what estimate her Department has made of the potential (a) cost of and (b) return per pound spent on each scheme in the (i) Strategic Road Network and (ii) Major Road Network and Large Local Major Programmes (A
Answer
Lilian GreenwoodThe total estimated cost of committed schemes in the Roads Investment Strategy (RIS) at planning stage (excluding Lower Thames Crossing) is £8.5 billion, and for schemes under construction the total is £4.1 billion. The total estimated cost of the schemes...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 2143) →