Written Question·Department for Transport·UIN 19018

Roads: Lancashire

Tabled: 10 December 2024
Answered: 16 December 2024

Question

Jerome Mayhew

ConservativeBroadland and Fakenham

To ask the Secretary of State for Transport, what estimate her Department has made of the completion date of the A585 Windy Harbour to Skippool RP2 project.

Answer

Lilian Greenwood
The schemes in question are in different stages as follows: Four schemes have been completed and are open to traffic.Scheme NameCompletion DateM621 Junction 1-7 EnhancementsCompleted September 2024A585 Windy Harbour to SkippoolCompleted March 2024A19 Down...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 19018) →