Written Question·Department of Health and Social Care·UIN 81818

Royal Lancaster Infirmary

Tabled: 14 October 2025
Answered: 20 October 2025

Question

Tim Farron

Liberal DemocratWestmorland and Lonsdale

To ask the Secretary of State for Health and Social Care, what assessment he has made of the potential impact of delays to rebuilding of the Royal Lancaster Infirmary on people in Westmorland and Lonsdale constituency.

Answer

Karin Smyth
The New Hospital Programme: plan for implementation was published on 20 January 2025 and sets out a credible, deliverable plan for the schemes in the New Hospital Programme (NHP). This plan will be delivered through five-year waves of investment and is ba...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 81818) →