Written Question·Department for Energy Security and Net Zero·UIN 18591

Sizewell C Power Station

Tabled: 9 December 2024
Answered: 17 December 2024

Question

Andrew Bowie

ConservativeWest Aberdeenshire and Kincardine

To ask the Secretary of State for Energy Security and Net Zero, what steps his Department is taking to construct grid connections for Sizewell C.

Answer

Michael Shanks
The policy position outlined in the National Energy System Operator (“NESO”) open letter [https://www.neso.energy/document/349496/download] (published 10th December 2024) indicates that, given Sizewell C received planning consent in July 2022, the existin...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 18591) →