Written Question·Department for Energy Security and Net Zero·UIN 15095
Sizewell C Power Station: Compensation
Tabled: 19 November 2024
Answered: 27 November 2024
Question
Carla Denyer
Green Party — Bristol Central
To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 16 October 2024 to Question 7946 on Sizewell C Power Station: Compensation, what (a) output in MWh his Department has assumed for Hinkley Point C and (b) discounting
Answer
Michael ShanksEDF’s assumed maximum capacity of HPC is 3.2GW, overlaid with assumptions for planned and unplanned outages. There isn’t a specific discounting rate applied to the First-of-a-Kind cost sharing. Instead, the payment for this cost sharing is included in the...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 15095) →