Question

Carla Denyer

Green PartyBristol Central

To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 16 October 2024 to Question 7946 on Sizewell C Power Station: Compensation, what (a) output in MWh his Department has assumed for Hinkley Point C and (b) discounting

Answer

Michael Shanks
EDF’s assumed maximum capacity of HPC is 3.2GW, overlaid with assumptions for planned and unplanned outages. There isn’t a specific discounting rate applied to the First-of-a-Kind cost sharing. Instead, the payment for this cost sharing is included in the...