Question
To ask His Majesty's Government what assessment they have made of the adequacy of water supplies for the Sizewell C nuclear facility, in light of the extension of the life of the Sizewell B nuclear facility and the increasing levels of water stress in Suf
Answer
An assessment of water supply formed part of the review of Sizewell C’s DCO application. Development consent was granted by the Secretary of State in June 2022. The company is working with water companies and other stakeholders to ensure a resilient suppl...
ⓘ