Written Question·Department for Energy Security and Net Zero·UIN 14687

Sizewell C Power Station: Finance

Tabled: 18 November 2024
Answered: 25 November 2024

Question

Wera Hobhouse

Liberal DemocratBath

To ask the Secretary of State for Energy Security and Net Zero, what proportion of funding from the public purse for Sizewell C has been (a) spent on and (b) committed to companies with headquarters in (i) the UK and (ii) what foreign countries.

Answer

Michael Shanks
The details of contracts agreed by Sizewell C with its suppliers are commercially sensitive. The project has made a commitment to spend 70 per cent of the construction value in the UK.