Written Question·Ministry of Housing, Communities and Local Government·UIN 37462
Social Rented Housing: Fire Prevention
Tabled: 11 March 2025
Answered: 19 March 2025
Question
Rachel Blake
Labour (Co-op) — Cities of London and Westminster
To ask the Secretary of State for Housing, Communities and Local Government, whether she has made an estimate of costs for housing associations related to the remediation of aluminium composite material cladding.
Answer
Alex NorrisIn 2018, government estimated that the cost of removing and replacing unsafe ACM cladding on 18m+ social residential buildings would be approximately £400 million. As of March 2025, 144 high rise buildings had entered the Social Sector ACM Fund. To date, ...
ⓘ