Written Question·Ministry of Housing, Communities and Local Government·UIN 37462

Social Rented Housing: Fire Prevention

Tabled: 11 March 2025
Answered: 19 March 2025

Question

Rachel Blake

Labour (Co-op)Cities of London and Westminster

To ask the Secretary of State for Housing, Communities and Local Government, whether she has made an estimate of costs for housing associations related to the remediation of aluminium composite material cladding.

Answer

Alex Norris
In 2018, government estimated that the cost of removing and replacing unsafe ACM cladding on 18m+ social residential buildings would be approximately £400 million. As of March 2025, 144 high rise buildings had entered the Social Sector ACM Fund. To date, ...

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 37462) →