Written Question·Department for Energy Security and Net Zero·UIN 73291
Solar Power
Tabled: 29 August 2025
Answered: 8 September 2025
Question
Martin Wrigley
Liberal Democrat — Newton Abbot
To ask the Secretary of State for Energy Security and Net Zero, whether the National Grid is under a (a) statutory and (b) regulatory obligation to process solar panel installation applications within a specified timeframe.
Answer
Michael ShanksFor solar installations of 3.68kW per phase, or below, no application is required. The Distribution Network Operator (DNO) must only be notified within 30 days of the installation. For larger projects, DNOs are required to provide a connection offer withi...
ⓘ