Written Question·Department for Energy Security and Net Zero·UIN 58191
Solar Power: Business Premises
Tabled: 9 June 2025
Answered: 17 June 2025
Question
Richard Fuller
Conservative — North Bedfordshire
To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the capacity of the National Grid to provide (a) timely and (b) adequate connections in the context of estimated trends in the level of adoption of rooftop sola
Answer
Michael ShanksOfgem recently made it easier for smaller generation projects (under 5MW in England and Wales) to connect, by removing the requirement for a transmission network impact assessment [1]. For larger projects, the implementation of connections reform will pri...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 58191) →