Written Question·Department for Transport·UIN 113247
South West Main Line: Devon
Tabled: 12 February 2026
Answered: 24 February 2026
Question
Martin Wrigley
Liberal Democrat — Newton Abbot
To ask the Secretary of State for Transport, what assessment she has made of the adequacy of the phase 5 rail resilience programme in the context of water levels in 2026.
Answer
Simon LightwoodWe remain committed to concluding the works necessary on this route to mitigate the remaining risks identified in the Southwest Rail Resilience Programme. Network Rail is commencing work on a drainage trial, removing water from a section of the cliffs bet...
ⓘ