Written Question·Department for Transport·UIN 55866
South Western Railway: Rolling Stock
Tabled: 30 May 2025
Answered: 9 June 2025
Question
Clive Jones
Liberal Democrat — Wokingham
To ask the Secretary of State for Transport, whether her Department has imposed contractual penalties on South Western Railway in relation to the time taken to deploy the Class 701 trains.
Answer
Simon LightwoodMy Department have not imposed contractual penalties on First MTR South Western Railway Trains Limited in relation to the time taken to deploy the Class 701 trains. I am extremely disappointed with how long the Class 701 introduction has taken and the Sec...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 55866) →