Written Question·Ministry of Defence·UIN 46154

Trident Submarines: Iron and Steel

Tabled: 17 April 2025
Answered: 30 April 2025

Question

Ben Obese-Jecty

Conservative — Huntingdon

To ask the Secretary of State for Defence, for what the reason the new Royal Navy Dreadnought Submarine programme will be built from steel imported from France.

Answer

Maria Eagle
United Kingdom (UK) submarine steel requirements continue to be sourced by our prime contractors from a range of UK and international suppliers. This reflects the need to source specific grades of steel, not all of which are available in the UK, and ensur...
ⓘ

This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 46154) →