Written Question·Department for Energy Security and Net Zero·UIN 83509
Wind Power: Celtic Sea
Tabled: 20 October 2025
Answered: 28 October 2025
Question
David Chadwick
Liberal Democrat — Brecon, Radnor and Cwm Tawe
To ask the Secretary of State for Energy Security and Net Zero, what information his Department holds on the planned timeline for (a) the first turbines to become operational and (b) other aspects of the projects awarded leases under the Crown Estate’s Ce
Answer
Michael ShanksThe Crown Estate has announced that Equinor and Gwynt Glas have now entered into agreements for lease to develop two new 1.5GW floating offshore wind projects in the Celtic Sea, which could be operational by the mid-2030s. The Crown Estate has estimated t...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 83509) →