Written Question·Department for Energy Security and Net Zero·UIN 20865
Wind Power: Fylde
Tabled: 17 December 2024
Answered: 20 December 2024
Question
Mr Andrew Snowden
Conservative — Fylde
To ask the Secretary of State for Energy Security and Net Zero, pursuant to the answer of 17 December 2024 to question 19898 on Wind Power: Fylde, what account the cost assessments have taken of existing infrastructure connecting Stanah to Penwortham.
Answer
Michael ShanksNational Energy System Operator (NESO) recommended the transmission infrastructure required to connect Morgan and Morecambe offshore wind projects to the grid as part of its Holistic Network Design (HND). In producing the HND, NESO assessed multiple onsho...
ⓘ
This is an extract from the Parliament API. Search the full answer on Parliament.uk (UIN 20865) →