My Lords, I am grateful for this opportunity to speak to my Amendment 2 and, I hope, to extract a reassurance from the Minister in this short debate. The amendment looks at how it is expected that nationally significant infrastructure projects will operate in the planning process as set out in the Bill. I am not satisfied with the way that the process has been set out, and therefore the thrust of Amendment 2 is to call for a potential review, during the course of which the Secretary of State should assess the
“cumulative impact of nationally significant infrastructure projects on … the environment”
and, in particular,
“residents living in areas in which such projects are being developed”.
I first raised this issue on one of the statutory instruments giving effect to the clean energy Act. I was very grateful to the then Minister, the noble Lord, Lord Hunt, for explaining to me how cumulative impact was meant to operate. It is clear that the cumulative impact of all the proposals set out in this Bill will be unexpectedly deep and wide for all those living in rural areas, yet their opportunities to be involved in the process will be curtailed if the Bill proceeds in its present form. This relates a little to the previous debate on the purpose of the Bill, because I believe that if the Bill is to function well—as I am sure the whole House would wish, having spent however many hours on it in Committee—it should ensure that it operates effectively.
I am deeply uneasy that the thrust of the proposals on nationally significant infrastructure projects are to benefit those living in the deep south of England and London, to the specific disbenefit of rural residents across the whole of the north of England. I hope noble Lords will appreciate that this amendment relates not so much to the housebuilding aspects of the Bill as to nationally significant infrastructure projects in the energy sector. I am thinking in particular of solar farms and the unimaginable scale currently foreseen.
This is not unique to this country. I follow developments in Denmark very closely. For the first time ever, a solar farm was going to be created in a deeply rural part of the northern mainland of Denmark, Jutland, but a very effective campaign, under rules in Denmark that are very favourable to this type of project, has been so successful that I am delighted to say that the project will not go ahead. I envisage similar concerns in this country once the full impact of the Bill is known.
My main concern, as the Bill is currently drafted, is this question to the Minister: should there not be a requirement that the cumulative impact assessment should be included in the local plan? My understanding is that currently that is not the case. If that is so, why is there no specific provision in either the planning applications or the Bill itself that such an assessment should be included in the local plan? Surely it is incumbent on developers, planners and the Planning Inspectorate to ensure that residents will see a joined-up planning application and that we will no longer see what we have seen historically.
For example, if there is an application for an offshore windfarm over here, people living in East Anglia think, “Well, that’s perfectly harmless, it won’t affect me, so that’s fine, it can go ahead”. Suddenly, the second stage of the planning application is to foist on them a major substation that they had no idea was going to be built on their doorstep. Then the third stage of the application is for overhead pylons, which is causing such great concern, particularly in East Anglia and other parts of eastern England: I am thinking here of east Yorkshire.
There have been two if not three Planning Inspectorate policy guidance publications, one in April last year and one in September last year. The Government are bringing forward their own proposals but, as I said earlier, the legislation is currently defective in this regard. What is most concerning about the September 2024 advice is that it specifically states:
“This advice is non-statutory. However, the Planning Inspectorate’s advice about running the infrastructure planning system and matters of process is drawn from good practice and applicants and others should follow our recommendations”.
So I have a further question for the Minister. If the advice published in September last year is non-statutory, how do we know that the advice and guidance will be followed? Surely it should be in the Bill, it should be statutory and it should be spelled out in plain English for all to see and understand, so that, when the fast-track process comes about, everyone knows. While the guidance was welcomed by civil engineers at the time it was published, lawyers were split as to how significant the changes would be for infrastructure developers. That makes me wonder whether it will have any effect whatever.
Therefore, in moving Amendment 2, I conclude by asking the Minister what assurance she can give the House that there will be joined-up planning applications in future. What checks will there be and what penalties will be imposed if the Planning Inspectorate’s advice is not followed in the fast-track procedure? I beg to move.