Speaking in the House of Lords on 19 June 2025
Debate
HS2 ResetContribution
I have spoken about our inheritance and James Stewart’s review, so let me finally turn to Mark Wild’s initial assessment, which lays bare the shocking mismanagement of the project under previous Governments—I will place a copy of his interim findings in the Library. He stated, in no uncertain terms, that the overall project, with respect to cost, schedule and scope, is unsustainable. Based on his advice, I see no route by which trains can be running by 2033 as planned. He reveals that costs will continue to increase if not taken in hand, further outstripping the budget set by the previous Government, and he cannot be certain that all cost pressures have yet been identified.
About Hansard
Hansard is the official verbatim record of proceedings in the UK Parliament. Every word spoken in the Commons and Lords is recorded and published — this page is a single contribution from that record.