My Lords, the amendments in this group are all on the extension of permitted development. My Amendment 77 concerns the extension of permitted development rights for low-voltage electricity networks. It intends to help this Government achieve their ambition of a clean, affordable and secure energy system by 2030.
The amendment would enable clearly defined and modest upgrades to be treated as permitted development. That includes the upgrading of electricity lines from single to three-phase, the alteration of conduct type, modest increases in pole height where required by regulation, the temporary placement of lines to facilitate works and the reinforcement of existing apparatus such as pole-mounted transformers.
This is not a revolution; it is about pragmatism. These are modest technical improvements that would make our national grid fit for the 21st century. This is not about new infrastructure on green fields. This is needed simply because our electricity network, built decades ago, is fundamentally ill-equipped for the task required of it. I am increasingly worried about the capacity of the low-voltage grid and the investment in it. This is needed to bring electricity to our homes and to ensure that we can make the transitions we need to make—having electric vehicles and installing heat pumps to help us hit our clean-power targets.
At present, these modest network upgrades face planning processes that can take months and sometimes even years, often longer than building the relevant generation plant itself. That results in higher costs and, in some cases, stranded investment. Companies across the energy sector report the same difficulties: planning bottlenecks, slow permissions and land-acquisition rules that lag behind those of gas, water and telecoms. That is not right; there should be a level playing field for these things.
Without reform, costs for paying for clean generators to turn down because the grid cannot handle their power could soar from £2 billion a year today to £8 billion by the end of the decade. These costs are absorbed by companies and passed on to bill payers, who face higher bills. We need to get this stuff done and it needs to work. It takes a series of minor but essential upgrades and technical adjustments to equipment, not new developments, and relieves them of lengthy planning processes. Nothing in this amendment would reduce safety. Electricity safety, quality and continuity regulations remain firmly in place under Section 37 of the Electricity Act 1989, which still governs overhead powerline consents. The safeguards endure. What would change is that we would no longer require the full machinery of a planning inquiry simply to raise a pole by a few feet or to replace a conductor with a modern equivalent.
The benefits are clear. First, it would speed up bureaucracy and get things moving. Secondly, it would lower costs and avoid delays. Thirdly, it would help us achieve our climate and renewable targets. Fourthly, it would provide us with security and resilience in the system and help get electricity to our front doorsteps, where we need it. This amendment would also require consultation on further measures, ensuring that where wider reforms are proposed, the public and stakeholders are fully engaged. I am not asking for a blank cheque here; this is a carefully drafted step forward. The Government have said that this Bill is central to their plan for clean power by 2030, and we agree. This amendment is modest and seeks to help unlock the arteries to make sure that electricity can be delivered.
As I have said, this is slightly complicated because it is a shopping list of very minor improvements. But it reminds me of the approach of British Cycling, which found that a number of very small incremental differences, if implemented as a philosophy, made huge fundamental strides and gains in its ability to win and achieve its goals. The same is true with these amendments. More importantly, these are reforms and changes that DNOs and wider industry bodies are calling for, and that they say they need to achieve clean power. This is about making sure that they can do what they signed up to do to help secure more investment and get things moving.
As I am opening this group, I will circle back to the other amendments at the end. I do not want to speak to other people’s amendments before they have introduced them.